AST Site Planning Checklist

Use this before you request pricing or submit a permit set. It helps surface the site questions that can change tank selection, installed cost, and the approval path.

There is no universal AST setback. Distances can change with liquid class, capacity, tank construction or protection, dispensing configuration, adopted code, and the authority having jurisdiction. Gather the inputs before anyone promises a number.

What to resolve before the tank is ordered

1. Jurisdiction

Who reviews the installation?

Identify the fire-code AHJ, environmental program, building or zoning reviewers, and any state AST registration or plan-review requirement.

2. Geometry

Does the system physically fit?

Map property lines, buildings, public ways, dispensers, adjacent tanks, fill location, vent outlets, vehicle paths, and service access.

3. Foundation

What does the tank sit on?

Foundation design is a site and engineering question. The tank listing does not create a universal concrete-pad thickness or make gravel automatically acceptable or unacceptable.

4. Containment

How will a release be controlled?

For SPCC-covered bulk storage installations, EPA requires capacity for the largest single container plus sufficient freeboard for precipitation. Fire-code requirements are a separate layer.

5. Delivery

Can a fuel truck fill it safely?

Check turning room, fill location, hose reach, traffic conflicts, grade, overhead restrictions, and a practical path for delivery personnel.

6. Dispensing

What happens after fuel is stored?

Plan pump power and flow, hose, reel, nozzle, meter, filtration, emergency shutoff, impact protection, electrical, controls, and monitoring.

Why the site answer comes before the tank answer

UL-listed tank construction and the complete installation are different questions. UL's own guidance notes that site-installed accessories and the final installation still need to satisfy the applicable installation code and authority. PEI's current RP200-24 treats site planning, foundations and anchorage, dikes, fill, gauge and vent systems, piping, electrical, environmental protection, testing, and documentation as distinct parts of an AST installation.

That is why a quote built from gallons alone can be misleading. A protected tank, double-wall construction, external containment, different dispenser location, or different foundation can materially change whether the system fits the site and what the installed project costs.

Now gathering supplier bids? Use the ungated AST RFQ checklist to compare tank equipment, dispensing scope, freight, installation and exclusions on the same basis.

Use the printable checklist on a site walk

The PDF is intentionally ungated. Print it, mark up a plan, or forward it to the person who owns facilities, safety, construction, or permitting. If you want help translating the answers into a starting specification, send the completed inputs with the project location.

Primary references

Scope: This checklist is a planning aid, not an engineered site plan, permit approval, legal opinion, or AHJ determination. Last verified: September 15, 2026.

How to use this checklist

Treat the site as part of the fuel-storage system.

The checklist is designed to surface project questions before pricing or delivery. It does not replace a site plan, engineered design, permit review, fire-code review, SPCC evaluation, or installer walk-through.

Before requesting quotes

Capture constraints that change the specification

Document the location, footprint, access, fuel use, delivery approach, foundation condition, dispensing needs, protection, utilities, and known jurisdiction contacts.

Before ordering

Resolve the questions that can force redesign

Confirm the applicable AHJ and approval path, final tank/listing, containment approach, delivery/offload plan, electrical scope, and installation responsibilities.

Worked field example

A fleet may know it wants roughly 2,000 gallons of diesel storage, but the site walk reveals a tight delivery turn, no practical forklift offload location, a short hose-reach requirement, and vehicle exposure on one side of the tank. Those facts can affect the final tank, protection, pump package, placement, and freight/offload plan before any permit question is even resolved.

Do not use the checklist as an approval certificate. Its job is to reveal the people, dimensions, constraints, and decisions that still need to be confirmed.

Related decisions

Use the checklist with the rest of the planning sequence.

Editorial scope: pre-order field planning for commercial aboveground fuel storage. Confirm final requirements with the applicable regulator, AHJ, engineer, installer, carrier, supplier, and other qualified professionals. Last updated: October 1, 2026.
Turn this checklist into a working project brief FuelReady helps capture capacity, dispensing, delivery and site decisions in one printable planning report. Use the free FuelReady tool →